Pages

Timeline

Porter Davis - Kallara 33 - Current

 

Construction (Currently at 96 Days of 212 Contracted)

 

Lock-Up Stage (53 Days ongoing)

12-Mar-2013 - Window Casements installed on Front Facade. Sliding Door Returned but how good? Bed2/3/4 Roofs have been leveled out.
08-Mar-2013 - Site Meeting with SS, He has agreed to fix all items outstanding. Still waiting for Sliding Door!
06-Mar-2013 - Site Cleaned
05-Mar-2013 - Bricks - Completed! Top Plate in Pantry Fixed
04-Mar-2013 - Bricks - Almost Complete, Truss company fixed roof truss properly this time that was previously fixed by making wall below load bearing!
01-Mar-2013 - Bricks - Garage Complete, Ensuite Spa Plumbing Fixed, Stacking Sliding Door Issues continue.
27-Feb-2013 - Bricks - Alfresco progress
26-Feb-2013 - Bricks - Garage Front Completed, Frame Truss Issues with Gurder over Study/Family/Kitchen
25-Feb-2013 - Bricks - Portico Completed
21-Feb-2013 - Bricks - Lounge / Study Wall Completed
20-Feb-2013 - Bricks - Bed Side of House Completed, Front Door Delivered, Plumber has come but still not fixed Ensuite Spa properly.
19-Feb-2013 - Pre Plaster Inspection
18-Feb-2013 - Insulation Installed - Electrical - Antenna Cabling Installed, More Brickwork
17-Feb-2013 - Electrical - Intercom System Chosen, Installed Noggings and Brackets.
16-Feb-2013 - Electrical - Installed Metal Bracks for Cat6, Theatre, and future GPOs, Heated Towel Rail Chosen
15-Feb-2013 - Fixing Carpenter - Completed, Cavity Sliding Door Modules Installed.
14-Feb-2012 - Fixing Carpenter - Walls Straighted, Bath Hobs Installed, More Brickwork Completed
13-Feb-2013 - Bricks Started - Plumbing Issues fixed except Ensuite Spa
11-Feb-2013 - Heating Duct Installed, Electrical AV Cabling Installed
10-Feb-2013 - Electrical - C-Bus Control Cabling Installed
09-Feb-2013 - Electrical - Cat6 Data Cabling Installed
08-Feb-2013 - Electrical - Completed - Catenary Wires for Cat6 cabling installed for weekend
07-Feb-2013 - Electrical - Rough In Continued - 240V cabling.
06-Feb-2013 - Electrical - Rough In Started - Data Points and FTTH
05-Feb-2013 - Roof Completed. Front & Laundry Frame Installed, Front Side Light broken. Frame issues fixed.
04-Feb-2013 - Roof Started
03-Feb-2013 - C-Bus, Cat6, C-Bus GPO, C-Bus Lighting Plans completed
02-Feb-2013 - Decied that I will install C-Bus and Cat6 cable now rather than after handover.
31-Jan-2013 - Roof Scaffolding Installed
30-Jan-2013 - House Wrapped
29-Jan-2013 - Plumbing - Rough In
23-Jan-2013 - Frame Stage - Independant Inspection

Frame Stage Completed (9 Days)

 

22-Jan 2013 - Frame invoice recieved. Facia installed
21-Jan 2013 - First Site Inspection with SS. Raised a number of issues with Frame/Slab to be resolved
18 Jan 2013 - Windows Installed, Roof Bracing, Roof Valleys installed.
17 Jan 2013 - Roof Truses completed. Roof Valleys installed, Cross Bracing support installed
16 Jan 2013 - Roof Trusses installed except Portico. Window Frames delivered
15 Jan 2013 - Frame Walls Completed. Roofing Rrusses delivered
14 Jan 2013 - Frame Strated - Master Bedroom, WIR, Pantry, Study, and BED2 completed
7 Jan 2013 - Nothing?

Builders Holiday (23 Days)


Chrismas Holiday Period. All works stopped.

Slab Stage (12 Days) 

 

21 Dec 2012 - Site Leveled and Excess Dirt removed
19 Dec 2012 - Slab Poured
18 Dec 2012 - Slab - Pre Frame, Waffel Pods, Reinforcing installed 
17 Dec 2012 - Plumbing Finished, Piers Set, Gravel Laid, Foam Delivered, Reinforcing Delivered
13 Dec 2012 - Plumbing - Stormwater
12 Dec 2012 - Power - Meter Cabinet - 3 Phase. (No Meter)
11 Dec 2012 - Temporary Fencing, Set out done (Pegs in Ground)
10 Dec 2012 - Official Site Start date - Site Cut Done
7 Dec 2012 - Taps Found on Property



Pre-Construction (Administration) 


5 Dec 2012 - Updated Final Drawings & BV2
30 Nov 2012 - Final Construction Drawings Signed
25 Oct 2012 - Land Settlement
15 Oct 2012 - Solicitor told settlement with in 14 days.
14 Oct 2012 - I find out from land developer that land has titled but they had forgotten to inform me.
 4 Oct 2012 - Land Titles
15 Jun 2012 - Contract
 8 Jun 2012 - Colour & Electrical Appointments, Updated Tile Layout
 7 Jun 2012 - Tile Selection
25 May 2012 - Tender Appointment
10 Apr 2012 - Initial Deposit paid to hold base price for Kallara 33

19 Mar 2012 - Title search paid to Solicitor
04 Feb 2012 - Land Deposit paid
14 Feb 2012 - Found local Solicitor
12 Feb 2012 - Land Crossover change requested
12 Feb 2012 - Land Contract Signed
07 Feb 2012 - Holding deposit paid on land
Mid-Jan 2012 - Revisit building idea 

Cayaman - Retired 


08 May 2011 - Plan to build Cayman Cancelled
08 May 2011 - Renovation works stoped
26 Feb 2011 - Begin Renovating Mum's House
Mid-Jan 2011 - Plan to Build Cayman with Mum

No comments:

Post a Comment